TRI facility · Utah
Price Ready Mix Plant
Price Ready Mix Plant in Wellington, UT reported 29 pounds of toxic chemical releases to EPA for 2024, over 99% to land, led by lead. It ranked 130th of 220 TRI facilities in Utah that year and 13,228th of 21,482 nationwide. (EPA Toxics Release Inventory, reporting year 2024; confirm it in this facility's EPA record.)
29lbtoxic releases, 2024
under 1%to air
1chemical reported, 2024
29lbof them carcinogens
0quarters in violation of 12 (ECHO)
What did Price Ready Mix Plant release in 2024?
- Air 0.2%
- Water 0.0%
- Land 99.8%
- Off-site disposal 0.0%
Of the 29 pounds released in 2024, under 1 pound went to air, 0 pounds to water, 29 pounds to land on site and 0 pounds to off-site disposal. 29 pounds (100%) were chemicals TRI flags as carcinogens (the OSHA list).
| Chemical | Released | Air | Water | Land | Off-site | Class |
|---|---|---|---|---|---|---|
| Lead | 29 | 0 | 0 | 29 | 0 | carcinogen, PBT |
Source: EPA Toxics Release Inventory basic data file, reporting year 2024, forms processed as of November 5, 2025. Confirm in EPA's ECHO facility report.
What does EPA's compliance record show for Price Ready Mix Plant?
EPA's compliance database (ECHO) links Price Ready Mix Plant to FRS facility 110070219983. In the last 12 quarters it was in violation of an environmental permit or rule in 0 of 12. ECHO records no inspection in the last five years. Regulators took 0 formal enforcement actions in five years.
| Program | Status now | Quarters in violation, last 12 | Formal actions (5 yr) | Penalties (5 yr) |
|---|---|---|---|---|
| Clean Water Act | No Violation Identified | 0 | 0 | $0 |
A violation is a permit or rule breach EPA or a state recorded; it is not a finding that the releases above were illegal. TRI releases are reported under a right-to-know law, not a permit.
Source: EPA Enforcement and Compliance History Online (ECHO) facility download, November 8, 2026. Confirm in ECHO detailed facility report.
How much waste did Price Ready Mix Plant manage, and where did it send it?
For 2024, Price Ready Mix Plant reported 29 pounds of production-related waste, the toxic chemicals it recycled, burned for energy, treated or released. It transferred 0 pounds off site, to recycling, energy recovery, treatment, disposal or a sewage treatment plant.
Source: EPA TRI basic data file 2024, sections 6 and 8 of the reporting form.
What can Price Ready Mix Plant's figures not tell you?
They are Price Ready Mix Plant's own estimates, filed under penalty of law, not EPA measurements, and a release is not a measure of what people nearby are exposed to. What TRI figures can and cannot tell you.
Sources: the EPA files behind this page
- EPA Toxics Release Inventory basic data files, reporting years 2019-2024, reporting year 2024 processed November 5, 2025: www.epa.gov
- EPA Toxics Release Inventory program (who reports, what counts as a release): www.epa.gov
- EPA ECHO Exporter (inspections, enforcement, compliance), file dated November 8, 2026: echo.epa.gov
- EPA Safe Drinking Water Act data download (SDWIS), quarter 2026Q3, October 14, 2026: echo.epa.gov
- EPA SEMS: all final, proposed and deleted NPL sites with dates, category and contaminants, report dated October 28, 2026: www.epa.gov